📚 Question Bank Q93 — Software Engineering
Tags
Software Engineering
Q93. Marks: +2.0 UGC NET Paper 2: Computer Science 2nd January 2026 Shift 1
📄 Passage
A project is planned for an enterprise accounting system with an estimated size 60 KLOC. The organization applies Basic COCOMO(Semi-Detached Mode with parameters:)
--Effort = 3.0 (KLOC) 1.0
--Development time = 2.5 (Effort) 1/2
--Average cost per person-month (pm) = $10,000
--A contingency margin of 10% effort is mandatory
--The client demands a detailed schedule if staff is capped at 15 engineers.
Answer the following 5 questions based on this paragraph.
What is the initial effort in Person-month (PM) before adding the contingency margin?
1. 240 PM
2.260 PM
3.180 PM ✓ Correct
4.200 PM
📄 All “Software Engineering” questions across papers
🏷 Change Tag for this Question