A project is planned for an enterprise accounting system with an estimated size 60 KLOC. The organization applies Basic COCOMO(Semi-Detached Mode with parameters:)
--Effort = 3.0 (KLOC) 1.0
--Development time = 2.5 (Effort) 1/2
--Average cost per person-month (pm) = $10,000
--A contingency margin of 10% effort is mandatory
--The client demands a detailed schedule if staff is capped at 15 engineers.
Answer the following 5 questions based on this paragraph.
If the staff is capped at 15 engineers what is the revised calendar duration?
1.20.0 Months
2.18.4 Months
3.13.2 Months ✓ Correct
4.22.0 Months