Q25. Marks: +2.0 UGC NET Paper 2: Computer Sc 23rd August 2024 Shift 1
Given a project with an estimated effort of 1500 person-hours and a team of 5 people, how many days will it take to complete the project, if each person works 8 hours a day?
1.30
2.37.5 ✓ Correct
3.40
4.45.5