A firm can produce two type of cloth say A and B. Three kind of wool are required for it, say red wool, green wool and blue wool. One unit length of type A cloth needs 2 yards of red and 3 yards of green wool. One unit length of type B cloth needs 3 yards of red wool, 2 yards of green wool and 2 yards blue wool. The firm has only a stock of 8 yards of red wool, 10 yards of green wool and 15 yards of blue wool. It is assumed that the income obtained from one unit length of type A and type B cloths are Rs. 30 and Rs. 50, respectively.

Which of the following will be appropriate objectives function for the given problem?
1.2x + 3y
2.3x + 2y + 2z
3.30x + 50y  ✓ Correct