Q26. Marks: +2.0 UGC NET Paper 2: Computer Science17th June 2023
Which of the following is used to determine the cost performance index? 
1.Budgeted cost of work performed - budget at completion
2.Budgeted cost of work performed ÷ budget at completion
3.Budgeted cost of work performed ÷ Actual cost of work performed ✓ Correct
4.Budgeted cost of work performed - Actual cost of work performed